Namami Gange
Sr Name of Sewerage Project Project Status District Scheeme Type Mode of Project AA&ES and date O & M Cost Work Component Agency Name Agreement Cost Date of Comp. As per Agreement Date of Start Expected Date of Completion.
Sanction Cost Work Cost Centage Date of Sanction
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17
1 I&D of Drains and Sewerage Treatment Plant works with 15 Years O&M at Sultanpur Completed Project Sultanpur NGP DBOT 70.180000 40.830000 2.59 Dec 24 2018 26.760000
M/s EIEPL- ABI(JV) 67.590000 May 29 2022 11/30/2019 12:00:00 AM Jun 10 2024
2 Etawah Sewerage Scheme ( Interception & Diversion Works) DIstt- Etawah Completed Project Etawah NGP1-NON EAP DBOT 140.600000 56.850000 3.90 Feb 28 2019 79.850000
M/s VVIP-BCPL Joint Venture 119.930000 Dec 31 2021 7/22/2019 12:00:00 AM May 31 2022
3 I&D and STP works at Kanpur-Pankha On Going Kanpur Nagar NGP HAM 967.230000 248.390000 31.05 Mar 12 2018 718.840000
M/s Kanpur River Management Pvt. Ltd. 708.700000 Oct 11 2021 10/11/2019 12:00:00 AM Jul 31 2025
4 I&D of Drains and STP works in Unnao (15MLD) On Going Unnao NGP HAM 102.200000 43.730000 3.22 Jul 28 2017 55.250000
M/s KRMPL Kanpur 68.680000 Jul 10 2021 10/11/2019 12:00:00 AM Oct 31 2023
5 Interception & Diversion (I&D) of drains and Sewerage Treatment Plant at Kasganj Completed Project Kasganj NGP1-NON EAP DBOT 76.730000 36.600000 2.49 Dec 24 2018 37.640000
M/s VVIP-BCPL Joint Venture 67.560000 Nov 30 2021 7/5/2019 12:00:00 AM Mar 31 2022
6 I&D of Drains and STP works in Shuklaganj (05MLD) On Going Unnao NGP HAM 65.180000 25.930000 1.90 Jul 28 2017 37.350000
M/s KRMPL Kanpur 38.870000 Jul 10 2021 10/11/2019 12:00:00 AM Dec 31 2023
7 Firozabad Sewerage Scheme ( Interception & Diversion Works) Distt Firozabad Completed Project Firozabad NGP1-NON EAP DBOT 51.080000 23.920000 1.63 Mar 1 2019 25.530000
M/s Shree- Tech Construction 42.430000 Jun 13 2021 11/14/2019 12:00:00 AM Aug 31 2021
8 Interception & Diversion (I&D) of Drains and Sewerage Treatment Plant at Moradabad zone 2 On Going Moradabad NGP HAM 118.690000 53.530000 3.52 Jul 23 2018 61.640000
Moradabad STP Pvt Ltd 113.850000 Jan 19 2025 1/20/2023 12:00:00 AM Jan 19 2025
9 Rehabilitation of Sewerage Infrastructure and Augmentation/upgradation of STP at Vrindavan Completed Project Mathura NGP1-NON EAP DBOT 42.820000 14.760000 1.18 Mar 29 2017 26.880000
M/s Hindustan Engineering, Lucknow 33.500000 Mar 31 2020 12/1/2018 12:00:00 AM Mar 31 2020
10 I and D of Sisamau and 5 other drains Completed Project Kanpur Nagar NGP DBOT 63.800000 57.630000 4.61 Oct 3 2016 1.550000
M/S G.S.J. Envo Limited 57.120000 Aug 22 2018 5/23/2017 12:00:00 AM
11 Rehabilation / Upgradation of Mathura Sewerage Scheme Completed Project Mathura NGP1-NON EAP HAM 460.450000 264.390000 8.78 Dec 13 2017 187.280000
M/s MWMPL Pvt Ltd 437.950000 Jan 14 2021 1/15/2019 12:00:00 AM Jun 14 2021
12 Agra Sewerage Scheme( Interception & diversion and STP works) On Going Agra NGP2-EAP HAM 842.250000 371.290000 25.40 May 6 2020 445.560000
M/s AWWMPL Pvt Ltd 582.840000 Apr 4 2025 4/5/2023 12:00:00 AM Apr 4 2025
13 I&D and STP works at Farrukhabad-Fatehgarh Completed Project Farrukhabad NGP HAM 261.120000 188.710000 6.98 Feb 9 2021 72.410000
M/S HNB Engineers Private Ltd. 252.410000 Jun 27 2024 6/28/2022 12:00:00 AM Nov 4 2024
14 Development of Sewage Treatment Plant at Bareilly Completed Project Bareilly NGP HAM 271.390000 139.440000 10.70 Jan 3 2019 121.250000
M/s EIEPL Bareilly Infra Engineers Ltd 233.720000 Aug 30 2024 8/31/2022 12:00:00 AM Aug 30 2024
15 Sewerage Works in Sewerage Dist 1 Kanpur Completed Project Kanpur Nagar NGP DBOT 430.490000 392.820000 23.81 Oct 18 2016 12.860000
M/S Shrishti Sam Lain Yogi JV 418.310000 Aug 16 2020 8/17/2017 12:00:00 AM Sep 30 2021
16 Interception Diversion and Treatment works at Bithoor Town Kanpur Completed Project Kanpur Nagar NGP DBOT 13.400000 10.750000 0.70 Oct 16 2017 2.450000
M/S C.S. ENTERPRISES 9.990000 Sep 19 2019 9/20/2018 12:00:00 AM Dec 31 2019
17 Rehabilitation and Operation & Maintenance of existing Sewage Treatment Infrastructure at Allahabad Uttar Pradesh under Hybrid Annuity based PPP Mode Completed Project PrayagRaj NGP HAM 904.000000 58.150000 0.00 Mar 9 2018 845.850000
M/s Prayagraj Water Private Limited 557.600000 Sep 15 2020 9/16/2019 12:00:00 AM May 31 2021
18 Interception, Diversion of Drains & Sewage Treatment Works at Ramnagar, Dist. Varanasi Completed Project Varanasi NGP DBOT 71.260000 21.890000 1.75 Jul 28 2017 45.910000
M/s SNET- N&S –RISPL JV 69.420000 Sep 10 2020 12/11/2018 12:00:00 AM Sep 10 2020
19 I&D and STP works for Naini (District-G) and Jhunsi works), Phaphamau (District-F) Completed Project PrayagRaj NGP HAM 767.590000 280.140000 21.66 May 19 2019 465.790000
M/s Prayagraj Water Private Limited 350.600000 Sep 15 2021 9/16/2019 12:00:00 AM Oct 31 2023
20 Kannauj Sewerage Scheme Phase II Completed Project Kannauj Non EAP DBOT 43.660000 37.770000 3.63 Feb 24 2011 2.260000
M/S Surendra Singh 39.650000 Apr 15 2018 9/20/2011 12:00:00 AM Apr 15 2018
21 I&D and STP works at Hathras Town On Going Hathras NGP DBOT 128.910000 70.480000 4.55 Jan 30 2023 53.880000
M/s Neercare India pvt KLtd JV M/s EMIT Group India Pvt Ltd JV EMS Ltd 119.050000 Jun 5 2026 9/6/2024 12:00:00 AM Jun 5 2026
22 Sewerage Treatment Plant for Assi-BHU Sewerage District at Ramana, Varanasi Completed Project Varanasi NGP HAM 161.310600 102.000000 8.16 Sep 21 2017 26.110000
M/s Varanasi STP Project Pvt. Ltd 153.150000 Nov 18 2019 2/19/2018 12:00:00 AM Nov 18 2019
23 I&D and STP works at Kosi Kalan Town, District Mathura On Going Mathura NGP DBOT 66.590000 31.240000 2.03 Oct 25 2022 33.320000
M/s R K Engineers Sales Ltd 53.600000 Jul 15 2026 10/16/2024 12:00:00 AM Jul 15 2026
24 Chhata Town Sewerage Scheme (I&D and STP works), District Mathura On Going Mathura NGP DBOT 56.150000 34.520000 2.23 Oct 25 2022 19.400000
M/s Shailesh Kumar J.V. 48.970000 Aug 11 2026 11/12/2024 12:00:00 AM Aug 11 2026
25 I&D and 13 MLD STP works at Vrindavan City On Going Mathura NGP DBOT 77.700000 39.900000 2.56 Oct 25 2022 35.240000
M/s SIMA -G D- N.P. (JV) 65.860000 Mar 10 2026 6/11/2024 12:00:00 AM Mar 10 2026
26 Pollution Abatement Works for River Saryu/Ghaghara at Faizabad town, District-Ayodhya (Interception & Diversion of Drains with 33 MLD STP) On Going Ayodhya NGP HAM 221.660000 109.030000 7.62 May 6 2021 105.010000
M/s Eco Protection Engineer Pvt Ltd 149.470000 Jan 2 2025 3/3/2023 12:00:00 AM Jun 20 2025
27 Interception, Diversion of Balance 7 drains and Augmentation of Rajapur STP capacity by 90 MLD (Sewerage District-D) at Prayagraj Uttar Pradesh under DBOT mode On Going PrayagRaj NGP DBOT 475.980000 242.850000 15.24 Jan 27 2023 217.890000
M/s Triveni Engineering and Industries 309.740000 Feb 23 2026 8/24/2024 12:00:00 AM
28 Mathura sewerage scheme (I&D and STP Works for balance drain) On Going Mathura NGP2-NON EAP HAM 292.560000 149.850000 9.61 Sep 7 2022 133.100000
M/s EIEL Mathura Infra Engineers Private Limited 240.010000 Nov 29 2026 11/30/2024 12:00:00 AM Nov 29 2026
29 Interception, Diversion of Balance 13 drains and Augmentation of Salori STP capacity by 43 MLD (Sewerage District-C) at Prayagraj Uttar Pradesh under DBOT mode On Going PrayagRaj NGP DBOT 331.750000 180.270000 11.22 Mar 14 2023 140.270000
M/s HNB Private ltd. - M/s Tirupati Cements Products (JV) 204.400000 Aug 18 2025 3/19/2024 12:00:00 AM
30 Interception, Diversion of Balance discharge of 02 drains and 50 MLD STP to Augment existing Treatment Capacity (80 MLD) Naini STP for Sewerage District-A at Prayagraj Uttar Pradesh under DBOT mode On Going PrayagRaj NGP DBOT 186.470000 83.710000 5.44 Sep 5 2023 97.320000
M/s JWIL-SSG (Joint Venture) 95.570000 Jul 3 2026 3/4/2025 12:00:00 AM
31 Prevention of Pollution of River Ramganga at Moradabad Completed Project Moradabad Non EAP DBOT 330.030000 278.850000 19.03 Feb 24 2011 32.170000
M/s Larsen & Toubro Limited 244.000000 Apr 20 2013 12/21/2011 12:00:00 AM Jun 1 2022
32 Sewerage Scheme for District A Completed Project PrayagRaj NGRBA EAP DBOT 299.390000 269.100000 19.75 Nov 11 2019 10.540000
M/s L&T Construction, WSW & C-IC, Network Project 292.290000 Apr 26 2018 4/27/2015 12:00:00 AM
33 Sewerage Scheme for District B Completed Project PrayagRaj NGRBA EAP DBOT 300.840000 278.280000 18.81 Nov 11 2019 3.750000
M/s EMS India Pvt Limited JV with M/s UEM India Pvt Ltd 280.860000 Jun 24 2019 6/25/2016 12:00:00 AM
34 Sewerage Scheme for District C Completed Project PrayagRaj NGRBA EAP DBOT 170.950000 154.010000 9.87 Sep 13 2019 7.070000
M/s Passavant Energy & Environment 165.410000 Apr 6 2017 4/7/2015 12:00:00 AM
35 Sewerage work in Sewerage District E of Allahabad Completed Project PrayagRaj NGRBA EAP DBOT 142.000000 126.700000 6.57 Feb 22 2011 8.730000
M/s UEM India Pvt Ltd 123.050000 Dec 6 2013 12/7/2011 12:00:00 AM
36 Sewer Network in District E of Allahabad Part-II Completed Project PrayagRaj NGRBA EAP DBOT 52.780000 48.900000 3.88 Sep 28 2016 0.000000
M/s EMS India Pvt Limited JV with M/s UEM India Pvt Ltd 46.690000 Jul 9 2018 4/10/2017 12:00:00 AM
37 14 MLD Capacity STP at Salori Allahabad Completed Project PrayagRaj NGRBA EAP DBOT 39.360000 24.250000 1.90 Jul 9 2020 13.210000
M/s UEM India Pvt Ltd 53.390000 May 13 2016 11/14/2014 12:00:00 AM
38 Pollution Abatement of Gomti River (Phase-II, Part-I) Lucknow On Going Lucknow NGP DBOT 264.670000 137.550000 8.53 Jan 30 2023 118.600000
M/s R.K. Engineers- Khilari Infrastructure (JV) 187.740000 Mar 13 2026 6/14/2024 12:00:00 AM
39 Sewerage and Non Sewerage Schemes for Pollution abatement of River Ganga at Allahabad District B&EU.P Completed Project PrayagRaj Non EAP DBOT 207.390000 187.530000 19.86 May 6 2010 0.000000
M/S HNB Engineers Private Ltd. 118.200000 Mar 31 2016 4/27/2015 12:00:00 AM Mar 31 2016
40 Sewerage, Sewage Treatment & Disposal for Ghazipur, U.P. Completed Project Ghazipur NGP HAM 152.830000 50.960000 4.08 May 6 2020 96.170000
M/s Mirzapur Ghazipur STPs Private Limited 140.940000 Jan 9 2024 4/10/2022 12:00:00 AM Oct 30 2024
41 Interception & Diversion (I&D) of Drains and Sewerage Treatment Plant at Jaunpur , U.P. Completed Project Jaunpur NGP DBOT 206.050000 119.010000 9.25 Feb 12 2019 63.910000
M/s SPML- PPPL JV 164.000000 Oct 20 2021 10/21/2019 12:00:00 AM Oct 20 2021
42 Pollution Abatement of Gomti River (Phase-II, Part-II ) Lucknow Tendaring Lucknow NGP HAM 351.030000 207.990000 13.14 Sep 19 2023 129.900000
0.000000
43 Interception & Diversion and STP at Mirzapur, U.P. Completed Project Mirzapur NGP HAM 129.080000 50.500000 4.04 May 28 2020 73.060000
M/s Mirzapur Ghazipur STPs Private Limited 151.580000 Jan 9 2024 4/10/2022 12:00:00 AM Jul 31 2024
44 Faecal Sludge Management for abatement of pollution in River Ganga at Chunar, Mirzapur, U.P. Completed Project Mirzapur NGP DBOT 2.700000 1.930000 0.29 Mar 7 2019 0.480000
M/S Elefo Biotech Pvt Limited 2.050000 Sep 8 2020 11/9/2019 12:00:00 AM Nov 30 2021
45 I&D and Treatment works for Assi-BHU Area (Phase-II), Varanasi On Going Varanasi NGP DBOT 308.090000 97.620000 7.81 Oct 19 2022 172.940000
M/s Enviro Infra Engineers limited MTS JV 151.550000 Dec 6 2025 3/7/2024 12:00:00 AM Dec 6 2025
46 I&D and STP Work in Kairana Completed Project Shamli CGF DBOT 78.420000 37.280000 2.63 Dec 7 2020 38.510000
M/s SIPL RKC JV 59.190000 May 27 2023 8/28/2021 12:00:00 AM Mar 31 2025
47 I&D and STP Work in Shamli On Going Shamli NGP DBOT 206.020000 103.190000 6.66 May 25 2023 96.170000
M/s R.K. Engineers Sales Ltd.-M/s Anand Constrwell Pvt. Ldt. (JV) 120.920000 Jan 13 2026 10/14/2024 12:00:00 AM Apr 13 2026
48 I&D of Drains at Ayodhya-Ayodhya. DBOT, NGP Completed Project Ayodhya NGP DBOT 37.670000 16.260000 1.10 Jun 11 2018 20.310000
M/S Satish kumar &co. 29.030000 Aug 16 2019 11/17/2018 12:00:00 AM Aug 16 2019
49 I&D and STP Work in Thanabhawan, Shamli On Going Shamli NGP DBOT 97.190000 55.630000 3.50 May 25 2023 38.060000
M/s R K Engineers Sales Ltd 63.720000 Jan 13 2026 10/14/2024 12:00:00 AM Apr 13 2026
50 Sewerage and Non Sewerage Schemes for Pollution abatement of River Ganga at Allahabad U.P District A Completed Project PrayagRaj EAP DBOT 97.950000 97.950000 0.00 May 6 2010 0.000000
M/s Ramky Infrastructure Ltd. 97.950000 Mar 7 2016 12/8/2010 12:00:00 AM Mar 7 2016
51 I&D and STP Work in Muzaffarnagar Completed Project Muzaffarnagar NGP HAM 234.030000 108.320000 7.33 Jan 13 2020 118.360000
M/S Muzaffarnagar STP Pvt Ltd 205.090000 Jun 3 2023 6/4/2021 12:00:00 AM Mar 31 2025
52 I&D and STP works at Bagpat Completed Project Baghpat NGP DBOT 77.360000 38.720000 2.66 Feb 19 2019 35.980000
M/s ICPL-OASIS-LNA (JV) 65.490000 Apr 7 2021 1/8/2020 12:00:00 AM Sep 30 2022
53 I&D and STP Work in Budhana Town Completed Project Muzaffarnagar Non EAP HAM 48.760000 25.100000 1.70 Feb 18 2019 21.960000
M/S Muzaffarnagar STP Pvt Ltd 41.280000 Jun 3 2023 6/4/2021 12:00:00 AM Oct 31 2023
54 I&D and STP Work in Banat, Shamli On Going Shamli NGP DBOT 48.710000 24.930000 1.58 May 25 2023 22.200000
M/s R K Engineers Sales Ltd 37.920000 Jan 13 2026 10/14/2024 12:00:00 AM Apr 13 2026
55 JICA Assisted Ganga Action Plan (GAP) Phase-II, Varanasi Completed Project Varanasi NGP DBOT 659.620000 629.160000 26.21 Jul 14 2010 0.000000
Pkg-1- M/s EMS Infracon Pvt. Ltd, Pkg-2- M/s UEM India Pvt. Ltd, Pkg-3- M/s Va Tech Wabag Ltd, Pkg-4- M/s Sriram EPC Ltd and Pkg-5- M/s Kirloskar Brothers Ltd 488.800000 Jun 27 2017 1/10/2013 12:00:00 AM Jul 22 2022
56 I&D and STP Work in Bantikhera and Babri village, Shamli On Going Shamli NGP DBOT 55.470000 29.410000 1.84 May 25 2023 24.220000
M/s R K Engineers Sales Ltd 41.910000 Jan 13 2026 10/14/2024 12:00:00 AM Aug 13 2026
57 I&D and STP works at Meerut On Going Meerut NGP2-EAP HAM 690.710000 363.780000 26.31 May 6 2020 280.190000
M/s. Meerut STP Pvt. Ltd. 369.739168 Nov 10 2026 11/11/2024 12:00:00 AM Feb 10 2027
58 I&D and STP works at Saharanpur Tendaring Saharanpur NGP2-EAP HAM 577.230000 266.340000 20.55 Jun 16 2022 290.340000
M/s Enviro Infra Engineers Ltd, Bhugan Infracon Pvt. Ltd. & Micro Transmission System, JV 343.880000
59 I&D and STP works at District-Hapur On Going Hapur NGP DBOT 49.060000 22.850000 1.42 Sep 19 2023 24.790000
M/s SKC Technocrat Pvt. Ltd (Formerly M/s Satish Kumar & Co.) & M/s. Geo Miller & Co. Pvt. Ltd. (JV) 39.281362 Feb 7 2026 11/8/2024 12:00:00 AM
60 FSSM In Dohrighat Town in Distt Mau DPR Mau Non EAP DBOT 0.000000 0.000000 0.00 Jan 1 1900 0.000000
0.000000
61 Interception and Diversion of Drains/Nala Falling in Varuna River and STP for Bhadohi Town Tendaring Sant Ravidas Nagar NGP2-NON EAP DBOT 127.260000 52.860000 4.23 Mar 6 2025 54.690000
0.000000
62 I&D and STP works for Durga Drain (Sewerage District-IV), Varanasi Tendaring Varanasi NGP2-NON EAP HAM 274.310000 107.700000 8.61 Mar 6 2025 97.500000
0.000000
63 Garhmukteshwar Sewerage Scheme. Completed Project Hapur Non EAP DBOT 46.510001 40.680001 3.25 Feb 24 2011 2.580001
M/s Anandi Lal Lalpuriya JV M/s Krishna Contractors JV M/s Khilari SS 32.710001 Apr 30 2018 9/7/2011 12:00:00 AM Apr 30 2018
64 Narora Sewerage Scheme Completed Project Bulandshahr EAP DBOT 48.450000 39.730000 2.26 Mar 4 2014 6.460000
M/s EMS India Pvt Limited JV with M/s UEM India Pvt Ltd 37.730000 Mar 31 2018 6/15/2015 12:00:00 AM Mar 30 2018
65 Anupshahar Sewerage Scheme Completed Project Bulandshahr EAP DBOT 75.790000 67.120000 5.27 May 19 2014 3.400000
M/s Laxmi Construction & Co JV M/s Backcone Enterprises JV M/s Oasis OPC Solution 69.300000 Sep 30 2018 5/19/2014 12:00:00 AM Sep 30 2018
66 I&D and STP Work in Deobandh Tendaring Saharanpur NGP DBOT 134.710000 67.420000 4.46 Jul 25 2024 62.830000
0.000000
67 Pollution Abatement of Gomti River (Phase-III ) Lucknow DPR Lucknow NGP DBOT 0.000000 0.000000 0.00 Jan 1 1900 0.000000
0.000000
68 I&D of Kashipur drain and Augmentation of Kodra STP by 28 MLD (Sewerage District - E) at Prayagraj DPR PrayagRaj NGP DBOT 0.000000 0.000000 0.00 Jan 1 1900 0.000000
0.000000
69 Gulaothi I&D works Tendaring Bulandshahr NMCG DBOT 50.980000 17.130000 1.37 Aug 28 2024 13.200000
0.000000
70 I & D and Treatment for Barhalganj 7 Drains Falling in Ghaghra River. DPR Gorakhpur NMCG DBOT 0.000000 0.000000 0.00 Jan 1 1900 0.000000
0.000000
71 I & D and Treatment for 8 Drains out of 9 Drains Falling in Rapti River DPR Gorakhpur NMCG HAM 0.000000 0.000000 0.00 Jan 1 1900 0.000000
0.000000
72 STP and I&D Work in Tanda nagar palika parishad ambedkarnagar DPR Ambedkar Nagar NMCG DBOT 0.000000 0.000000 0.00 Jan 1 1900 0.000000
0.000000
73 Aligarh Sewerage Scheme (I&D And STP Works) Tendaring Aligarh NMCG HAM 496.020000 240.020000 15.12 Oct 21 2024 240.880000
0.000000
74 Interception & Diversion Of 14 Untapped Drains Of Kanpur City (Along with Supplementary Works) Tendaring Kanpur Nagar NGP2-NON EAP DBOT 138.110000 97.170000 7.77 May 2 2025 2.030000
0.000000
75 Prevention of Pollution of River Ramganga at Moradabad under zone-3 & 4 construction of Interception & Diversion (I&D) of Drains and Sewerage Treatment Plant Tendaring Moradabad NMCG HAM 420.410000 238.530000 14.14 May 2 2025 181.870000
0.000000
76 Pollution Abatement of Gomti River (Phase-IV), Lucknow DPR Lucknow NMCG DBOT 0.000000 0.000000 0.00 Jan 1 1900 0.000000
0.000000
77 Balance Darins Tapping and Augmentation of SPSs at Agra City DPR Agra NGP DBOT 0.000000 0.000000 0.00 Jan 1 1900 0.000000
0.000000 May 31 2024 5/31/2024 12:00:00 AM May 31 2024
78 Upgradation and Capacity Augmentation of Existing 80 MLD STP Dinapur in Varanasi DPR Varanasi NGP DBOT 0.000000 0.000000 0.00 Jan 1 1900 0.000000
0.000000
79 I&D and STP works at Pt Deen Dayal Upadhyay Nagar Chandauli Tendaring Chandauli NGP2-NON EAP HAM 262.780000 95.000000 7.60 Jan 22 2025 129.670000
0.000000
80 DPR OF 08 KLD Fecal Sludge Treatment Plant At Dalmau Raibareli Tendaring Rae Bareli NMCG DBOT 4.400000 3.010000 0.18 Aug 28 2024 1.210000
0.000000
81 Pollution Abatement Of Gomti River (Phase 1 Part 1) Lucknow On Going Lucknow NGP DBOT 240.930000 123.450000 6.97 Jul 29 2024 110.510000
M/s R.K. Engineers- Khilari Infrastructure (JV) 187.900000 Jun 6 2026 9/7/2024 12:00:00 AM
82 Interception and Diversion of Additional flow from Sasurkhaderi Drain and Augmentation of Numayadahi STP in Sewerage District-B, Prayagraj DPR PrayagRaj NGP DBOT 0.000000 0.000000 0.00 Jan 1 1900 0.000000
0.000000
83 Faecal Sludge Management for Pollution abatement of river Ganga at Manikpur, Pratapgarh Tendaring Pratapgarh Non EAP DBOT 8.560000 5.730000 0.19 Jan 22 2025 1.900000
0.000000